The costs of staying with coal

The new power unit in Turów, bulit for PLN 4.3 billion, was shut down after just one month of operation. It is not adjusted to the quality of coal from Turów mine. The complex in Bogatynia is already generating huge costs. At the same time, sustaining its operations deprives the region of the opportunity to benefit from the EU funds for the Just Transition. 

1. Nearly 5 billion for damaged block

The Turów block was put into operation on May 15, and the failure occurred on June 16. Since then, it has been out of service. Mateusz Kokoszkiewicz wrote about the failure of the Turów unit for Gazeta Wyborcza. The journalist quotes one of the power plant employees:

“People had been coming to this block to repair the equipment for a long time.  The block was operating on a backup system, and all automatic functions had to be turned off as the whole system was poorly executed. The block is not adapted to the quality of coal from Turów mine. The quality of this raw material is too poor for the needs of the new unit [1].

“PGE is avoiding answering questions about the unit’s failure,” reports Wyborcza. Rzeczpospolita says that “PGE is explaining that this is a planned outage and a standard action to ensure continuous and failure-free operation of the unit for the coming years,” but this is contradicted by “the industry” [2]. The costs that will have to be incurred to repair the unit and adapt it to Turów coal are not known.

Huge money earmarked for building and repairing the block should be transferred for the just transition of the region and for creating new jobs. The plan announced by PGE to operate the mine and power plant until 2044 is unrealistic due to climate goals of the European Union and the rising price of CO2 emission allowances. As think-tank Instrat demonstrated, the National Power System can easily function without Turów after 2026[3].

“Unfortunately, almost 5 billion PLN instead of the new unit could have been spent on a fair transformation of the region, thanks to which the inhabitants would benefit and not the companies building this power unit,” comments Katarzyna Kubiczek, project coordinator of the Eco-Union organization.

Sources:

  1. https://wroclaw.wyborcza.pl/wroclaw/7,35771,27341308,elektrownia-turow-ma-awarie-bo-jest-zle-zaprojektowana-nowy.html
  2. https://www.rp.pl/Wegiel/307199945-Kopalnia-Turow-rozpoczela-walke--o-przetrwanie.html
  3. https://instrat.pl/wp-content/uploads/2021/03/Instrat-Droga-do-celu-v1.3.pdf

2. Continuing to operate will costs a lot 

Turów’s operation also involves paying for investments to protect the Czechs from further theft of their water by the open pit and dust. The costs are not small. As Barbara Oskińska reports in Parkiet:

 “Underground water is to be protected by an anti-filtration screen from potential outflow from the Czech territory towards the mine. In fact, it is a deep hole stretching over 1 km with a special sand-silt mixture. The screen, whose construction will cost PLN 17 million, will start operating in September. Windproof screen, which costs around PLN 20 million, will be a barrier that is meant to protect Czechs from dust. Noise protection will be provided by an earth rampart built along the Polish-Czech border.

That is not enough for the Czechs as they are negotiating money for further investments aimed at eliminating risks connected with the Polish open-pit mining. Originally, the Polish government agreed to pay EUR 40-45 million. However, negotiations are still ongoing” [1].

What is worse, it is not certain that the 17 million screen, which is planned by PGE, will in fact protect the inhabitants of the Czech border region from the loss of water. Dr. Sylwester Kraśnicki, hydrogeologist, pointed out that “the screen minimizes the impact of the opencast, but does eliminate it completely. So, it is difficult to say whether the screen that PGE wants to build will solve the problem” [2]. So, it is possible that further investments will be needed. 

Talks with the Czech Republic are still ongoing. The next round is scheduled to begin on Thursday, July 22. For now, the specter of financial penalties has receded. Earlier, the Czechs had asked CJEU to impose a fine of five euro per day on Poland for failing to cease production, as ordered by the CJEU. 

Sources:

  1. https://www.parkiet.com/Surowce-i-paliwa/307199990-Dla-kopalni-Turow-rozpoczal-sie-nowy-etap--walka-o-przetrwanie.html
  2. https://oko.press/w-jaki-sposob-turow-odsysa-wode-czechom-tlumaczymy-krok-po-kroku/

3. Transformation profitable for everyone

Turów’s operation already require gigantic financial outlays. Extending it beyond 2026 or 2030 will mean further costs. Above all, it will deprive the region of the opportunity to benefit from huge money from the Just Transition Fund. In June 2021, the European commissioner for environment, oceans and fisheries, Virginijus Sinkevičius told TVN24:

“The Just Transition Fund is available to Poland in a significant part. However, the Polish authorities were the one who decided to extend mining until 2044 which is not in line with the objectives of the Just Transition Fund and which excludes support for the Jelenia Góra region with Turów and Bogatynia, where no transformation is planned before 2030. The Polish government still has a chance to propose an earlier date to move away from coal which must be consistent with the Just Transition Fund, and then the funds will be available.” 

Source:

  1. https://tvn24.pl/biznes/ze-swiata/virginijus-sinkevicius-o-kopalnii-turow-w-rozmowie-z-maciejem-sokolowskim-program-7-dni-unia-5132284
×
 
stopturow
Luxembourg, 20 September 2021 - Statement from the Europe Beyond Coal campaign groups on (...)
The local Greenpeace group from Upper Lausitz, together with many inhabitants of the region (...)
It is time to build bridges across borders for a sustainable future. We want (...)
On 9 August 2021, the report of the United Nations Intergovernmental Panel on Climate (...)
Negotiations between Poland and the Czech Republic are still in progress, however the details (...)
The new power unit in Turów, bulit for PLN 4.3 billion, was shut down (...)
The fourth round of talks between the Polish and Czech governments over the Turów (...)
Concerned Czech citizens have written a letter to Virginijus Sinkevičius, European Commissioner for the (...)
więcej
2021-06-29
Poland has to show its goodwill in the negotiations
2021-06-04
Why are you burning our future?
2021-06-04
The problem with Turów and polish coal – 10 facts
2021-05-24
European Court of Justice orders halt to operations at controversial (...)
2021-05-24
Stoping mining in Turów will not lead to a blackout
2021-05-14
License that will destroy the region
2021-04-30
RES could be the future of Turów
2021-04-29
PGE myths vs reality
2021-04-28
Other countries may join in the complaint against Turów
2021-04-27
Polish response to the Czech request
2021-04-14
Poland won't reach out to its neighbours
2021-04-01
Escalation of conflict
2021-03-02
Turów case as a failure of enforcement of EU law? (...)
2021-02-17
Enough with PGE arrogance
2021-02-03
Despite criticism from the EU, Poland wants to extend mining (...)
2021-02-02
PGE vs rest of the world
2021-01-21
Opencast lignite mining in Turow causes dispute at EU level (...)
2021-01-18
Lignite’s agony artificially delayed
2020-12-21
An open door to the Court of Justice
2020-12-14
Turów is a threat to our cultural heritage
2020-12-11
The Polish response to Turów case is "unacceptable"
2020-12-11
Pressure makes sense. ICPO has decided that Turów is an (...)
2020-12-11
People are tweeting about Turów
2020-11-26
A problem taller than skyscrapers
2020-11-09
Turów operations against the precautionary and prevention principles
2020-10-29
News about Turów is spreading in Germany
2020-10-20
Who will pay for water for the Turów opencast?
2020-10-12
Will Poland face the European Court of Justice because of (...)
2020-10-05
PGE needs to put their cards on the table
2020-09-28
PGE caught in between
2020-09-17
Shoulder to shoulder against the opencast mines. Video report from (...)
2020-09-11
In solidarity against Turów and Garzweiler lignite mines. International kayaking (...)
2020-08-07
Turów dispute continued
2020-07-24
Europe divided on the Tripoint
2020-07-14
PETI Committee press release
2020-07-10
Let’s meet at the Three-Nations-Point
2020-07-03
Leaving lignite is inevitable
2020-06-26
PGE deprives region’s opportunity to develop
2020-06-19
Turów violates EU water regulations
2020-06-04
Turoszow transition
2020-05-22
Lot of noise about Turów in June
2020-05-15
The European Union takes a closer look at the license (...)
2020-05-07
Opencasts under scrutiny of Rzeczpospolita
2020-05-04
EURACTIV: Czech lawsuit against Poland?
2020-04-15
Post-mining lakes in Turów and Bełchatów
2020-04-14
About how the Czechs carried coal through the mountains and (...)
2020-04-14
EC replies to the parliamentary question
2020-04-08
Banco Santander supports PGE
2020-04-07
Does mBank burn coal from Turów mine?
2020-04-06
How PGE Turów uses shock
2020-04-06
Emissions do not stop at the border
2020-04-01
The crisis is a dead cert
2020-03-27
The city of Zittau appeals
2020-03-25
Poland prolonged the mining licence for Turów
2020-03-24
Official PGE statement from 24 March 2020
2020-03-22
Thirst for justice: communities take on coal giant for stealing (...)
2020-03-20
Response to the parliamentary question on Turów mine
2020-03-06
Petition in the European Parliament
2020-03-05
Czech citizens filed the petition
2020-02-21
Sign petition!
Licencja Creative Commons Content collected on the site are available under a Creative Commons license